The dry volume method
Wet concrete is less in volume than the dry materials that go into it, because the voids fill up. To account for this we multiply the wet volume by a dry volume factor of 1.54 (some engineers use 1.52–1.57).
Cement (m³) = wet volume × 1.54 × cement part ÷ sum of parts Cement (kg) = cement m³ × 1,440 kg/m³ · bags = kg ÷ bag sizeExample: 1 m³ of M20 (1 : 1.5 : 3). Dry volume = 1.54 m³ and the parts add up to 5.5. Cement = 1.54 ÷ 5.5 = 0.28 m³ × 1,440 = 403 kg ≈ 8.1 bags of 50 kg. Sand = 0.42 m³ and aggregate = 0.84 m³. With w/c 0.5 you need about 202 litres of water.
| Grade | Nominal mix | Cement per m³ | Typical use |
|---|---|---|---|
| M10 | 1 : 3 : 6 | 222 kg (4.4 bags) | Blinding, levelling course |
| M15 | 1 : 2 : 4 | 317 kg (6.3 bags) | PCC, non-structural floors |
| M20 | 1 : 1.5 : 3 | 403 kg (8.1 bags) | RCC slabs, beams, columns (mild exposure) |
| M25 | 1 : 1 : 2 | 554 kg (11.1 bags) | Structural RCC |
Important: nominal mixes are fine for small works. For M25 and above, structural codes (IS 456, EN 206, ACI 211) recommend a design mix made by a lab.
Frequently asked questions
What is the ratio of M20 concrete?
M20 nominal mix is 1 : 1.5 : 3 (cement : sand : coarse aggregate) by volume, with a water–cement ratio of about 0.5.
How many bags of cement are in 1 m³ of M20?
About 8 bags of 50 kg (403 kg) using the dry volume method with a factor of 1.54.
Why multiply by 1.54?
Dry materials shrink by about 54% in volume when mixed with water, because the fine particles fill the voids between larger ones. 1.54 turns wet volume into dry volume.
What does M in M20 mean?
“M” stands for mix, and 20 is the characteristic compressive strength in N/mm² (MPa) after 28 days.
How much does a bag of cement weigh?
50 kg in South Asia, the Middle East and much of Europe; 25 kg in the UK; 94 lb (42.6 kg) for US portland cement; 20 or 40 kg in Australia.
Last updated 2026-11-26. These results are estimates for planning and ordering. Structural designs must be checked by a qualified engineer.